The shipment of 4 tanks each around 100 tons, and some smaller parts, was delivered with chartered project vessel MV Eemslift Ellen.
The maximum capacity for the vessel is 4000 tons. Our cargo was not very heavy but it was voluminous.
With 2 cranes of each 150 tons SWL our cargo was lifted safely ashore.
From quayside to building site the voluminous cargo was carefully moved with a SPMT, a flexible vehicle with 18 axls, and carefully lifted off with cranes and placed on site.
Tangen Logistics responsbilities were: Coordination with local port authorities, traffic authorities, suppliers of cranes and heavy machinery, delivery of the tanks to building site. Coordination with charterer of vessel and owner of the cargo.
The cargo is production equipment for the processing industry.